Sejaung Enterprise built a concrete drainage system for a longhouse area at Sungai Goh, in the Kapit Division. We were main contractor for a government agency. Work started on 12 August 2024 and was certified complete on 28 November 2024, ahead of the February 2025 contract completion date.

Role
Main contractor
Work
Concrete drainage system
Client
Government agency
Period · Status
Aug–Nov 2024 · Completed