Work story · Main contractor

School fence at SK Nanga Bawai

Sejaung Enterprise installed a perimeter fence at SK Nanga Bawai, in the Kapit Division. We were main contractor for a government agency. The site was handed over on 20 July 2026, and the school confirmed the work complete on 28 August 2026, within the 40-day contract period.

Role
Main contractor
Work
School perimeter fence
Client
Government agency
Period · Status
Jul–Aug 2026 · Completed

What we did

  1. Cleared the site and brought in the equipment.
  2. Drove mangrove piles, 100 mm × 3 m, under every post footing.
  3. Put up a 1.5 m fence: 50 × 50 × 6 mm steel angle posts, set in Grade 20 concrete footings.
  4. Fitted 50 mm diamond mesh (No. 10 SWG) with 3 PVC-coated tension wires. The bottom of the mesh is set in a Grade 20 concrete beam, with 3 lines of barbed wire 0.3 m above the mesh.
  5. Installed a sliding gate (1.8 m high, 3 m wide) and a single-leaf gate (1.05 m wide, 1.5 m high).

We took the photos below on site in July and August 2026.

Sejaung Enterprise was the main contractor for this work.