Sejaung Enterprise built a new concrete drain at Rh. Anthony, Merit, in the Kapit Division. We were main contractor for a government agency. The contract started in May 2025, and the work was certified complete on 11 September 2025.

Role
Main contractor
Work
New concrete drain
Client
Government agency
Period · Status
May–Sep 2025 · Completed

The agency's Certificate of Practical Completion (CPC) confirms the work was satisfactorily completed on 11 September 2025, ahead of the November 2025 contract end date. The defects liability period runs to September 2026. We took the photos below on site in September 2025.