Work story · Main contractor
New concrete drain at Rh. Anthony, Merit
Sejaung Enterprise built a new concrete drain at Rh. Anthony, Merit, in the Kapit Division. We were main contractor for a government agency. The contract started in May 2025, and the work was certified complete on 11 September 2025.
- Role
- Main contractor
- Work
- New concrete drain
- Client
- Government agency
- Period · Status
- May–Sep 2025 · Completed
The agency's Certificate of Practical Completion (CPC) confirms the work was satisfactorily completed on 11 September 2025, ahead of the November 2025 contract end date. The defects liability period runs to September 2026. We took the photos below on site in September 2025.



Sejaung Enterprise was the main contractor for this work.